Versailles Grand Parc Greenways

FMp_vgp_01

The initial study performed in 2012 honed the master plan for the development of the greenways, defining and specifying a network of cycle-friendly itineraries that would create a soft transport network for leisure use. The project in its entirety helps in the development and planning of this land area at the metropolitan and local level, enhancing its natural and agricultural landscapes, its heritage and the dynamics of urban projects. The project is divided into different phases, the first of which crosses the Versailles plain and follows the Bièvre valley, thus linking all the communes of Versailles Grand Parc.

 

FEASIBILITY STUDIES AND PROJECT MANAGEMENT
Master plan 2012 / Project phase 1 2014

Contracting authority
Versailles Grand Parc district council
Project manager
Florence Mercier Paysagiste mandated landscape architect, Degouy roads and utilities
Budget
€20m
Surface area
Length: 70km